Site last updated: Wednesday, November 27, 2024

Log In

Reset Password
MENU
Butler County's great daily newspaper

Stadium, renovation project timelines presented

The Knoch School Board got its first look at the timeline for its $35 million stadium and high school renovation project.

John Pappas, the project’s construction manager, told the board that bids for the renovations and upgrades at the high school will be advertised in early April, with the hope of having contracts in place by May.

While the bulk of the work in the project will take place in summer 2024, work on bathrooms and the new entrance and high school offices on the northeast corner of the building will begin at the end of May 2023.

Construction of the new kitchen, common area and seating steps also will begin at that time, Pappas said.

The final work at the high school, the renovation of the technology areas of the high school, is estimated to begin in April 2025.

A portion of this story is shared with you as a digital media exclusive. To read the full story and support our local, independent newsroom, please subscribe at butlereagle.com.

More in Digital Media Exclusive

Subscribe to our Daily Newsletter

* indicates required
TODAY'S PHOTOS