ROUTE 228 PROJECTS

The following Route 228 projects are in the preliminary engineering phase:

Ekastown West

Final design: $281,400 from 2019 budget

Utility relocation: $689,600 from 2020 budget

Right of way acquisition: $2.12 million from 2020 budget

Construction: $6.86 million from 2022 budget

TOTAL: $9.95 million

Three Degree Road

Final design: N/A

Utility relocation: $1.44 million from 2019 budget

Right of way acquisition: $4.63 million from 2019 budget

Construction: $21.74 million from 2020 budget

TOTAL: $27.83 million

Balls Bend

Final design: $522,500 from 2019 budget

Utility relocation: $570,100 from 2021 budget

Right of way acquisition: $3.62 million from 2021 budget

Construction: $27.4 million from 2022 and 2023 budgets

TOTAL: $32.12 million

Pittsburgh Street to Franklin Road

Final design: $1.29 million from 2019 budget

Utility relocation: $1.85 million from 2022 budget

Right of way acquisition: $8.86 million

Construction: $76.93 million

TOTAL: $88.95 million